This judgment text has undergone conversion so that it is mobile and web-friendly. This may have created formatting or alignment issues. Please refer to the PDF copy for a print-friendly version.

In the GENERAL DIVISION OF

THE high court of the republic of singapore
[2024] SGHC 50
Originating Application No 1176 of 2023
Between
Hiap Seng Building Construction Pte Ltd
Applicant
And
Hock Heng Seng Contractor Pte Ltd
Respondent
grounds of decision
[Building and Construction Law — Statutes and regulations — Date of service of payment response — Section 11(1)(b) of the Building and Construction Industry Security of Payment Act]
[Equity — Estoppel — Promissory estoppel — Contractor objecting that it served an invalid payment response — Whether contractor was estopped from making that objection for failure to speak up earlier]
[Building and Construction Law — Dispute resolution — Legal proceedings — Whether adjudication determination was severable]

This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports.
Hiap Seng Building Construction Pte Ltd

v

Hock Heng Seng Contractor Pte Ltd
[2024] SGHC 50
General Division of the High Court — Originating Application No 1176 of 2023
Wong Li Kok, Alex JC
13 December 2023, 5 January 2024
27 February 2024
Wong Li Kok, Alex JC:
Introduction
1 This was an application under s 27 of the Building and Construction Industry Security of Payment Act 2004 (2020 Rev Ed) (the “SOPA”) (read with O 36 r 3 of the Rules of Court 2021) to set aside the Adjudication Determination dated 18 October 2023 (the “Determination”) in Adjudication Application No. SOP/AA199 of 2023 (the “Adjudication”), and by extension, the Order of Court (DC/ORC 2721/2023) dated 6 November 2023 made in DC/OA 178/2023 granting the respondent leave to enforce the Determination in the same manner as a judgment or order of the court.
2 The key issue the application sought to address was whether a defective payment response should lead to the setting aside of an adjudication determination under the SOPA. In the same vein, I also had to determine if the party issuing a defective payment response was estopped from relying on its own defective payment response to set aside an adjudication determination.
Facts
3 The applicant was the main contractor for a project to build a residential apartment (the “Project”). Pursuant to a sub-contract between the applicant and the respondent (the “Sub-contract”), the respondent was engaged as the sub-contractor for the Project. For avoidance of doubt, unless indicated otherwise, all references to the “respondent” refers to the party in this setting aside application (as opposed to a respondent in an adjudication under the SOPA).
4 On 5 July 2023, the respondent served its Payment Claim No. 15 (the “Payment Claim”) on the applicant for completed works. On 27 July 2023, the applicant submitted a document labelled “Progress Payment certificate No. : 02 for claim no. 15” (the “Payment Response”) to the respondent, certifying the total value of works carried out as S$15,758.51 (exclusive of GST) and S$16,861.60 (inclusive of GST). The respondent then issued to the applicant a tax invoice dated 1 August 2023 for the sum of S$16,861.61 (inclusive of GST) (the “Tax Invoice”).
5 On 7 August 2023, the applicant issued to the respondent the final accounts for the Sub-contract and the Project. This confirmed the total value of works carried out as S$15,758.51 (exclusive of GST). Having not received payment nor any other response from the applicant on the Tax Invoice, on 8 September 2023, the respondent commenced the Adjudication against the applicant pursuant to s 12(1) of the SOPA which provides that a claimant is entitled to make an adjudication application if there is non-payment of the accepted response amount. In the adjudication application lodged by the respondent for the Adjudication (the “Adjudication Application”), the respondent sought a sum of S$16,861.61 (inclusive of GST) on the basis that the applicant had failed to pay the sum certified in the Payment Response. The applicant subsequently filed its adjudication response on 18 September 2023 (the “Adjudication Response”).
6 In the Determination, the Adjudicator ruled in favour of the respondent and determined that the applicant shall pay the sum of S$17,019.19 (inclusive of GST) (the “Adjudicated Amount”) to the respondent. This consisted of a determined amount of S$15,758.51 and an amount of S$1,260.68 representing 8% GST on the determined amount. The Adjudicator noted that the Adjudicated Amount differed from the amount of S$16,861.60 in the Payment Response because the latter had computed the GST amount as S$1,103.10, when 8% GST was S$1,260.68.
The parties’ cases
The applicant’s case
7 The applicant sought to set aside the Determination under s 27(6)(d) of the SOPA (“the adjudication application … was not made in accordance with the provisions of this Act”) and s 27(6)(e) of the same (“the adjudicator failed to comply with the provisions of this Act in making the adjudication determination”). There were two grounds raised by the applicant:
(a) First, the Payment Response was not a valid payment response within the meaning of the SOPA.
(b) Second, the Adjudicator acted ultra vires in awarding the Adjudicated Amount which was greater than what was claimed by the respondent.
8 On the first ground, the applicant contended that there was no express provision in the Sub-contract as to the date or period for the service of a payment claim. That being the case, s 10(3)(b) of the SOPA (read with s 10(2)(a)(ii) of the same and regs 5(1) and 5(3) of the Building and Construction Industry Security of Payment Regulations (2006 Rev Ed) (the “SOPR”)) would deem the Payment Claim served on 5 July 2023 to have been served on the last day of the calendar month in which it was actually served, ie, 31 July 2023.
9 Based on the applicant’s case, it then follows that the Payment Response served by the applicant on 27 July 2023 could not have been a valid payment response under s 11(1)(b) of the SOPA which requires a respondent named in a payment claim to respond to “a payment claim served”, since there cannot be a payment response before a payment claim comes into being. In the absence of a valid payment response, the respondent’s entitlement to lodge an adjudication application did not arise under s 12(1) of the SOPA. The Adjudication Application could not have been validly made, as required under s 13(3)(a) of the SOPA, within 7 days “after the entitlement … to make an adjudication application [arose] under section 12”. As the Adjudication Application was not made in accordance with the provisions of the SOPA, this engaged s 27(6)(d) of the SOPA. Further, by failing to reject the flawed Adjudication Application under s 16(3) of the SOPA which requires an adjudicator to reject an adjudication application not made in accordance with s 13(3)(a) of the SOPA, the Adjudicator did not comply with the provisions of the SOPA, and this engaged s 27(6)(e) of the SOPA.
10 Relatedly, the applicant argued that the doctrine of estoppel as set out in Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317 (“Audi Construction”) did not apply. It was not estopped from arguing the invalidity of the Payment Response because it made no representation as to its position on the defective Payment Response. While Audi Construction noted that silence may amount to an unequivocal representation where there was a duty to speak, the applicant raised the defect of the Payment Response on the first occasion that it could under the SOPA (ie, in its Adjudication Response). It thus complied with its duty to speak.
11 In relation to the second ground, the applicant relied on Rong Shun Engineering & Construction Pte Ltd v CP Ong Construction Pte Ltd [2017] 4 SLR 359 (“Rong Shun”) to argue that the scope of the Adjudicator’s jurisdiction was framed by the response amount stated in the Payment Response and accepted by the respondent in its Adjudication Application. Accordingly, the Adjudicator acted ultra vires in determining a higher Adjudicated Amount on his own accord.
The respondent’s case
12 Regarding the validity of the Payment Response, the respondent counter-argued that the SOPA does not invalidate a payment response that predates the deemed service date of a payment claim, as s 11(1)(b) of the SOPA serves as a deadline for the service of a payment response (as opposed to a start date). This meant that while the deadline for serving the Payment Response only started running after the deemed date of service of the Payment Claim, the Payment Response could be validly served starting from the actual date of service of the Payment Claim (irrespective of the deemed date of service). According to the respondent, this interpretation was consistent with the legislative intent of the SOPA, which is to facilitate cashflow by achieving a quick and efficient resolution to payment disputes in the construction industry.
13 On estoppel, the respondent argued that the applicant’s early service of the Payment Response (which the applicant argued is invalid), together with the applicant’s subsequent silence, amounted to an unequivocal representation that the applicant would not exercise its right to serve a payment response until after the Payment Claim was deemed served. In other words, the applicant was estopped from relying on its own invalid Payment Response as a ground for setting aside the Determination. The applicant had a duty to speak when it had to serve its Payment Response or when the Tax Invoice was issued, but the applicant continued to stay silent. As a result, the respondent missed the opportunity to submit an adjudication application premised upon the lack of a payment response. The applicant was thus estopped from invalidating the Determination based on the defective Payment Response.
14 Finally, the respondent contended that the sum stated in the Payment Response, the Tax Invoice and the Adjudication Application was incorrect, as there was a mathematical error in calculating the GST amount. The 8% GST on the certified sum of S$15,758.51 ought to have been reflected as S$1,260.68 and not S$1,103.10. Relying also on Rong Shun and additionally on ss 17(4)(c), 17(4)(d) and 17(4)(h) of the SOPA (which provides that an adjudicator may consider, amongst others, the documents filed for the adjudication and any other relevant matter), the respondent argued that it was within the power of the Adjudicator to make arithmetical corrections and award a higher (and correct) sum to the respondent.
Issues to be determined
15 The issues to be determined are as follows:
(a) whether the Payment Response was valid;
(b) whether the applicant was estopped from challenging the Determination based on the invalidity of the Payment Response; and
(c) whether the Adjudicator acted ultra vires in awarding the Adjudicated Amount.
Issue 1: The Payment Response was invalid
16 It was undisputed that the Sub-contract did not prescribe the date of service of a payment claim. In such cases, s 10(2)(a)(ii) of the SOPA provides that a payment claim must be served “not later than … the date prescribed for the purpose of this subsection if the contract does not contain such terms”. The prescribed date for the purposes of s 10(2)(a)(ii) of the SOPA is in regs 5(1) and 5(3) of the SOPR which provide that:
5. —(1) Where a contract does not contain any provision specifying the time at which a payment claim must be served or by which such time may be determined, then a payment claim made under the contract must be served by the last day of —
(a) the month following the month in which the contract is made; or
(b) subsequent month.
(3) In this regulation, “month” means a period of time beginning on the first day of each of the 12 calendar months into which a year is divided, and ending on the last day of each of these months.
17 Reading s 10(2)(a)(ii) of the SOPA and regs 5(1) and 5(3) of the SOPR together, a payment claim under the Sub-contract must be served not later than the last day of the calendar month. Section 10(3)(b) of the SOPA states that “a payment claim that is served before the prescribed date mentioned in subsection 2(a)(ii) is deemed to have been served on that date.” The effect of these sections has been explained in Asia Grand Pte Ltd v A I Associates Pte Ltd [2023] SGHC 175 (“Asia Grand”) at [35]:
… Accordingly, the effect of ss 10(2)(a)(ii) and 10(3)(b) is that if the contract does not contain terms that specify, or provide for the determination of, a service date or service period, then any payment claim will be deemed to have been served on the last day of the calendar month in which it was served, regardless of when it was actually served.
[emphasis added]
18 That being the case, the Payment Claim which was actually served on 5 July 2023 would be deemed to have been served on 31 July 2023 under the SOPA. This was not disputed by the parties. It was also not in dispute that the Sub-contract does not provide the date of service of a payment response. Section 11(1)(b) of the SOPA sets out the default timeline for the submission of a payment response in such situations:
11. —(1) A respondent named in a payment claim served in relation to a construction contract must respond to the payment claim by providing, or causing to be provided, a payment response to the claimant —
(b) where the construction contract does not contain such provision, within 14 days after the payment claim is served under section 10.
[emphasis added]
19 The natural reading of s 11(1)(b) of the SOPA is that a payment response must be served starting from the date “after the payment claim is served under section 10” (which is deemed to be the last day of the calendar month pursuant to s 10(3)(b) of the SOPA) and before the end of 14 days from that deemed service date of a payment claim. The respondent’s proposed interpretation – that s 11(1)(b) of the SOPA only provides a deadline for the submission of a payment response as opposed to a period of time within which a payment response must be served (see above at [12]) – is inconsistent with the ordinary meaning of the word “within”.
20 Where the Parliament intended to only stipulate an end date, this is made clear in the language of the SOPA. For instance, s 11(2) of the SOPA requires any payment response in relation to a supply contract to be served “by the due date” [emphasis added]. Another example is s 10(2)(a)(ii) of the SOPA (see above at [16]) which uses the phrase “not later than”. The finding that s 11(1)(b) of the SOPA contemplates both the start date and the end date for the service of a payment response is supported by the explanation by the then Minister of State for National Development, Mr Zaqy Mohamad, at the Second Reading of the SOPA Amendment Bill on 2 October 2018, and his explanation is helpfully summarised in Asia Grand at [41]:
… the respondent’s deadline for the payment response will only start running from the date stipulated in the contract for service of payment claims or from the last day of the service period …
[emphasis added]
21 I disagreed with the respondent that a strained reading of s 11(1)(b) of the SOPA is necessary to uphold the overall intent of the SOPA to promote cashflow efficiency in the construction industry. Strict compliance with the timelines laid out by the SOPA is as much part of the driving force behind the SOPA as promoting cashflow efficiency. This is because adherence to the SOPA timelines is what facilitates the legislative intent of cashflow efficiency. As noted in Asia Grand at [1]:
[SOPA] was enacted to introduce a regime for interim payments and a procedure to resolve payment disputes that facilitate cash flow in the construction industry. The legislative purpose is achieved by creating a statutory scheme for payment for work done or materials supplied that is effected “through an expeditious process that requires strict adherence to timelines”: see the High Court decision of Libra Building Construction Pte Ltd v Emergent Engineering Pte Ltd [2016] 1 SLR 481 …
[emphasis added]
22 In that regard, the applicant’s interpretation of s 11(1)(b) of the SOPA would better cohere with the purpose of the SOPA to provide consistent and fixed timelines for the service of payment claims and payment responses. The following passage from Asia Grand is particularly apposite (at [42]):
… In the context of a contract like the present one, wherein the parties do not stipulate timelines for the service of payment claims or payment responses, it is reasonable for the respondent's deadline for payment response to be fixed to run only from the last day of the calendar month. This provides certainty for the respondent and helps to facilitate the timely service of payment responses. A payment process that keeps to regular timelines that run from a consistent day in each month keeps the SOPA mechanism running smoothly, prevents the missing of deadlines due to inadvertence, and minimises disputes. As a corollary, this also relieves a respondent from the need to constantly keep track of payment claims that are not served according to any stipulated contractual timelines.
[emphasis added]
23 Adopting the applicant’s reading of the SOPA, I agreed that the Payment Response submitted on 27 July 2023 predated the deemed date of service of the Payment Claim and was hence defective within the meaning of s 11(1)(b) of the SOPA.
24 For completeness, I noted the applicant’s argument that the Payment Response was merely a “purported” or draft payment response and should not have been taken by the respondent as a payment response at all. Looking at the correspondence between the parties during the time the Payment Response was sent and received, there was no indication by the applicant that the Payment Response was merely a draft, even after the issuance of the Tax Invoice. The Adjudicator also noted that there was no evidence that parties have discussed or wished to discuss further on the Payment Response. It was immaterial that the Payment Response was unsigned, as there is no requirement under the SOPA for a payment response to be signed. I agreed with the Adjudicator and found that the Payment Response was intended to be a payment response.
Issue 2: The applicant was estopped from challenging the invalid Payment Response
The entire Determination was not tainted by the invalid Payment Response and/or the Adjudicator’s flawed ruling on its validity
25 Before addressing estoppel, two further preliminary points had to be addressed:
(a) first, whether the invalid Payment Response invalidated the entire Determination; and
(b) second, whether the Adjudicator’s flawed ruling on the validity of the Payment Response tainted the entire Determination.
26 I answered both in the negative, as elaborated below.
27 I concluded that the invalid Payment Response did not taint the entire Adjudication. This defect only interfered with the Adjudicator’s substantive jurisdiction, but not his threshold jurisdiction. The latter would render the Adjudication invalid ab initio. As the Adjudicator’s threshold jurisdiction remained intact, the estoppel doctrine was free to operate.
28 As explained by the Court of Appeal in Grouteam Pte Ltd v UES Holdings Pte Ltd [2016] 5 SLR 1011 (“Grouteam”) at [49], there are certain procedural defects that are so fundamental that they go towards an adjudicator’s threshold jurisdiction. These render the adjudication determination null and void from the outset:
[A]n adjudicator would not have been validly appointed if there was in fact no payment claim or no service of a payment claim. In such a case, there would be no basis at all to appoint an adjudicator, and any such appointment would be void and without effect in law. This is a consideration of the adjudicator’s jurisdiction at the threshold because without a payment claim or service of such a claim, there is no basis at all for an adjudicator to be appointed in the first place.
[emphasis in original in italics; emphasis added in bold italics]
29 Other than a situation where there was no payment claim or no service of a payment claim, an adjudicator may also be found to have no threshold jurisdiction if a payment claim fell outside the purview of the SOPA from the outset (Far East Square Pte Ltd v Yau Lee Construction (Singapore) Pte Ltd [2019] 2 SLR 189 (“Far East”) at [67]). Examples of such payment claims include those made pursuant to contracts that are excluded from the scope of SOPA under s 4 (Far East at [60]).
30 By contrast, where a purported payment claim has been served but is defective by reason of non-compliance with the SOPA, “it would go to the adjudicator’s substantive jurisdiction” [emphasis in original] (Grouteam at [49]). However, the appointment of the adjudicator remains valid, and the adjudicator’s threshold jurisdiction remains unaffected. Nonetheless, the adjudication determination may be liable to be set aside if there has been a breach of the SOPA that would warrant the invalidation of the entire adjudication (Grouteam at [50]).
31 In the present case, the invalid Payment Response would fall under the category of cases where only the substantive jurisdiction of the adjudicator is impugned. In Far East at [57], the Court of Appeal drew a distinction between “(a) an invalid and/or invalidly served payment claim; and (b) a payment claim that is outside the ambit of the SOPA from the outset”. Similarly, the Payment Response which did not satisfy s 11(1)(b) of the SOPA would amount to an invalid payment response, but one which still fell within the scope of the SOPA. This procedural defect would only go towards the Adjudicator’s substantive jurisdiction, with his threshold jurisdiction still intact. That being the case, even though I disagreed with the Adjudicator’s reasoning on the validity of the Payment Response, the estoppel doctrine could still operate to prevent the applicant from making submissions on the defects of the Payment Response.
32 As to the second preliminary issue, I found that the Adjudicator’s erroneous decision on the validity of the Payment Response did not taint the entirety of the Determination. Under s 27(8)(a) of the SOPA, the court in a proceeding to set aside an adjudication determination may set it aside “in whole or in part”. In the present case, the parts of the Determination that address the early service of the Payment Response are confined to specific paragraphs that are isolated from the other issues. Accordingly, those paragraphs can be severed and set aside without affecting the flow and coherence of the rest of the Determination.
The requirements of estoppel were satisfied
33 I agreed with the respondent that the applicant was estopped from challenging the Determination on the basis of its invalid Payment Response.
34 The elements of an estoppel in the SOPA context are set out in Audi Construction at [57]:
… It requires unequivocal representation by one party that he will not insist upon his legal rights against the other party, and such reliance by the representee as will render it inequitable for the representor to go back upon his representation …
35 Crucially, mere silence or inaction by a party will not normally amount to an unequivocal representation, unless there is a duty to speak (Audi Construction at [61]). When this duty to speak may arise was explained in some detail in Audi Construction at [61]–[62]:
61 … [W]hether there is a duty to speak is a question which must be decided having regard to the facts of the case at hand and the legal context in which the case arises. … The expression “duty to speak” does not refer to a legal duty as such, but to circumstances in which a failure to speak would lead a reasonable party to think that the other party has elected between two inconsistent rights or will forbear to enforce a particular right in the future, as the case may be. We emphasise that this is not the subjective assessment of the other party but an objective assessment made by reference to how a reasonable person apprised of the relevant facts would view the silence in the circumstances, though unsurprisingly, the parties’ relationship and the applicable law which governs it will be a critical focus of the court’s assessment of whether those circumstances exist.
62 … In the context of an adjudication under the Act, a claimant and respondent are parties to a contract, on which the regime of the Act is superimposed. The contract and the Act define the rights the parties have in relation to each other. In our view, these are rights which are in principle capable of being elected and whose exercise is capable of being forborne.
[emphasis added]
36 Counsel for the applicant argued that the submission of the Payment Response could not have amounted to an unequivocal representation as to the applicant’s position on the invalid Payment Response. This was based on s 11(4) of the SOPA which provides that a submitted payment response may be varied, provided that the varied payment response is submitted by the date or within the period that a payment response is to be served under s 11(1) of the SOPA, or within the dispute settlement period under s 12(5) of the SOPA. In other words, despite having served the Payment Response, the applicant was still entitled to serve another payment response prior to the stipulated deadline. Hence, contrary to the respondent’s argument, the Payment Response was not an unequivocal representation that the applicant would “forbear to exercise its right not to serve a payment response until after a payment claim was deemed served”.
37 The applicant further argued that, under the SOPA process, the applicant’s duty to speak did not arise until it was required to provide its Adjudication Response. Having raised its complaint regarding the defective Payment Response at the first available opportunity (ie, in the Adjudication Response), the applicant argued that it had discharged its duty to speak.
38 In the explicit context of the SOPA, I agreed with the applicant’s position that the duty of a respondent (in an adjudication) to speak would only arise when an adjudication response is submitted. There is no additional mechanism under the SOPA for the respondent to raise objections following the issuance of a tax invoice by the claimant. However, in the context of the present facts, I found that the applicant’s duty to speak arose earlier. I set out below a summary of the chain of correspondence between the parties:
(a) Following the submission of the Payment Claim by the respondent, the applicant sent its Payment Response by email, stating “Kindly see attached payment cert for your reference”.
(b) The respondent then sent an email attaching the Tax Invoice and informing the applicant that a hard copy would be sent to the applicant’s headquarters.
(c) The applicant replied with “Kindly see attached Final Account for your endorsement”.
39 Looking at this exchange, I agreed with the respondent that the applicant’s duty to speak against the invalid Payment Response arose once the actual deadline for the service of a payment response was reached (as provided under s 11(1)(b) of the SOPA), or when the Tax Invoice was issued to the applicant. The applicant received the Tax Invoice without raising any objection and allowed the time within which it had to properly submit a payment response to lapse. Such silence and inaction amounted to an unequivocal representation by the applicant that it would not insist on its legal right to serve its payment response later (ie, within 14 days after the deemed date of service of the payment claim) and thus would not seek to invalidate any adjudication on the basis of an invalid payment response.
40 The respondent relied on that representation to its detriment, making it inequitable for the applicant to go back on its representation. The following passage from Audi Construction at [64] is apposite in illustrating the application of the estoppel doctrine where a party failed to object to an invalid payment claim:
The respondent may also communicate his intention to forbear to exercise his right to object to the payment claim’s validity. The claimant, in turn, may in reliance on that communication omit to re-file a payment claim which rectifies the filed payment claim’s defect, if any. If the respondent later attempts to impugn the validity of the filed payment claim, the claimant may by then, to his detriment, have missed the opportunity to re-file a rectified payment claim. Indeed, the claimant may have decided not to re-file because the respondent had acted consistently with the position that the payment claim was valid. In such a case, the respondent may in principle be estopped from raising that objection …
41 By analogy, the above analysis on an invalid payment claim would also apply to the invalid Payment Response. Here, in reliance on the applicant’s representation, the respondent missed the deadline to file an adjudication application on the basis that the applicant “fail[ed] to provide a payment response” (s 12(2)(b) SOPA). Hence, the respondent could only submit its Adjudication Application on the basis of an accepted response amount that is not fully paid.
42 As the Court of Appeal in Audi Construction made clear at [69], parties should not be incentivised to act in a manner that defeats the very purpose of the SOPA. Audi Construction also refers to an objective assessment of when a reasonable person should consider that a duty to speak would arise (see above at [35]). The facts of the current case fell exactly within the parameters considered by Audi Construction as to when such a duty to speak arose. The early and erroneous submission of the Payment Response was of the applicant’s own doing. The applicant had ample opportunity to raise its objection in a timely way. By having chosen not to do so, the applicant should not be able to subsequently raise this issue to invalidate the Determination purely on technical grounds. It was estopped from doing so.
Issue 3: The Adjudicator was acting ultra vires in awarding a higher amount than that stated in the Payment Response
43 I turn to the final issue on jurisdiction. I concluded that the Adjudicator had acted ultra vires in awarding the Adjudicated Amount of S$17,019.19, which was higher than the amount of S$16,861.60 stated in the Payment Response.
44 Both parties relied on Rong Shun to advance their positions. In that case, the adjudicator was found to have exceeded its jurisdiction in deciding on a retention sum claim which was not included in the applicant’s payment claim (Rong Shun at [103]). The respondent sought to distinguish Rong Shun on the basis that the present case does not involve a new head of claim, but only an arithmetic correction which the Adjudicator was permitted to do per ss 17(4)(c), 17(4)(d) and 17(4)(h) of the SOPA. To reproduce the relevant parts, s 17(4) of the SOPA provides that an adjudicator “may only have regard to the following matters”:
(c) the payment claim to which the adjudication application relates, the adjudication application, and the accompanying documents thereto;
(d) the payment response to which the adjudication application relates (if any), the adjudication response (if any), and the accompanying documents thereto;
(h)  any other matter that the adjudicator reasonably considers to be relevant to the adjudication.
45 I found that the respondent’s reliance on s 17(4) of the SOPA did not assist its case. The respondent had nailed its colours to the mast on the amount of S$16,861.60 on multiple occasions:
(a) The respondent’s Tax Invoice issued to the applicant stated the sum of S$16,861.61 as the “Net Amount Due”.
(b) The Notice of Intention to Apply for Adjudication stated that the respondent had “accepted the response amount and issued a Tax Invoice for the sum of $16,861.61”, and that it “intends to apply for adjudication on the response amount of $16,861.61 (inclusive of GST)” as no payment has been made of that amount.
(c) In the respondent’s Adjudication Application, the nature of the dispute was indicated as “Accepted response amount not fully paid”, and the amount claimed was “SGD 16,861.61 (inclusive/exclusive of GST)”.
(d) In the written submissions for the Adjudication itself and throughout the Adjudication process, the respondent did not seek to vary or correct its claimed amount.
I noted the discrepancy in the stated amount across the parties’ documents. Between S$16,861.60 and S$16,861.61, I adopted the former figure since this was the quantum referred to in the Payment Response and the Determination.
46 The Adjudicated Amount was never sought by the respondent. In fact, as submitted by the applicant, the amount of S$16,861.61 was the respondent’s “accepted response amount” which formed the basis of the Adjudication Application. In that regard, I considered the principle of fair notice as explained in Rong Shun applicable to the present case. Rong Shun highlighted the importance of a payment claim in “fix[ing] the parameters of the substantive content of an adjudication application” (at [101]), the rationale being one of fairness to the respondent in an adjudication (at [102]):
… A respondent must be able to ascertain from the payment claim with completeness and certainty – at the time it receives the payment claim – each claim which it will have to address in its payment response if it chooses not to satisfy that claim …
47 Transposing this to the present context, the documents listed above at [45] similarly fixed the parameters of the Adjudication. There was absolutely no notice given to the applicant that it had to meet a claim for a higher amount than S$16,861.61 in the Adjudication. I concluded that the Adjudicator exceeded his jurisdiction in awarding the Adjudicated Amount.
48 However, this did not warrant setting aside the entirety of the Determination, as the court has the power to sever an adjudication determination for jurisdictional errors. In particular, it was noted in Rong Shun at [155(e)] that:
… the court may modify the text of the adjudicator’s determination in order to achieve severance if the court is satisfied that it is effecting no change in the substantial effect of the adjudication determination after accounting for the jurisdictional error and its necessary editorial consequences.
49 In the present case where only the excess amount of S$157.59 (S$17,019.19 – S$16,861.60) required severance, modification of the Determination would achieve this purpose without affecting the substantive content of the Determination.
Conclusion
50 In conclusion, the setting aside application was allowed in part with the Adjudicated Amount in the Determination reduced from S$17,019.19 to S$16,861.60. The excess amount of S$157.59 was ordered to be released, from the payment into court, to the applicant.
51 I made no order as to costs. Though the respondent had succeeded in the application in substance, most of the arguments surrounded the issue on the validity of the Payment Response. This issue and the jurisdictional issue arising from the Adjudicated Amount were both raised by the applicant’s counsel in its letter to the respondent’s counsel prior to the filing of this application to set aside the Determination. In light of this, the respondent could have conceded on those two issues and focused its case on estoppel. Since the respondent nevertheless chose to argue all the issues, I determined that no order as to costs was a fair outcome.
Wong Li Kok, Alex
Judicial Commissioner
Benny Santoso, Sim Chee Siong (Rajah & Tann Singapore LLP) for the applicant;
Gan Guo Bin, Quek Seng Soon Winston (Winston Quek & Company) for the respondent.
Back to Top

This judgment text has undergone conversion so that it is mobile and web-friendly. This may have created formatting or alignment issues. Please refer to the PDF copy for a print-friendly version.

Version No 1: 27 Feb 2024 (12:45 hrs)