This judgment text has undergone conversion so that it is mobile and web-friendly. This may have created formatting or alignment issues. Please refer to the PDF copy for a print-friendly version.
GPE Pte Ltd |
Siemens Pte Ltd |
This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher’s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports. |
S/N | Description of alleged delay | Plaintiff’s case | Defendant’s case | Decision |
Jangkrik Project | ||||
1. | Delay in issuance of Weld Procedure Specifications (“WPS”) | There was an email from the Indonesian authorities (“MIGAS”) where the plaintiff was instructed to stop work (the “6 May Email”) because they did not have the correct WPS.
| The 6 May Email actually states that MIGAS did not want the work to be held up and therefore the plaintiff could go ahead with conducting the Welder Qualification Testing (“WQT”) notwithstanding the erroneous reference numbers on the WPS. | It is not disputed that the first WPS issued by the defendant had erroneous WPS numbers. However, the 6 May Email states that notwithstanding this error, the plaintiff could go ahead with carrying out the WQT for its 25 welders.
The plaintiff’s complaint therefore is that the defendant had delayed in re-issuing corrected WPS, which in turn prevented the plaintiff from qualifying new welders in the interim from 28 April 2015
to 25 June 2015. I accept the plaintiff’s evidence that MIGAS was only willing to relax the WPS requirements for the first 25 welders who were qualified, but for subsequent welders the defendant would have to obtain a new set of WPS with corrected numbers. Indeed, the defendant did not issue a corrected set of WPS until 25 June 2015.
Given that there is prima facie evidence of idle manpower and machinery from Morris’ oral testimony, I therefore send this claim down for assessment to determine the loss (if any) resulting from idle manpower and machinery from 28 April 2015 to 25 June 2015 because the new welders were prevented from being qualified. |
2. | Delay in issuance of drawings | The inference should be that the drawings are to be pushed to the plaintiff by the defendant. The defendant has signed off on the schedule. The schedule shows the scheduled start dates and when the drawings should be received.
prima facie evidence of delay in the issuance of drawings by the defendant. Serial nos. 7, 8 and 9 all indicate that the drawings were received after the scheduled start date. Therefore, there is | The Jangkrik contract states that “all the relevant drawings will be issued progressively in line with the project schedule”. This indicates that the plaintiff would have to request for the drawings before they are issued by the defendant. | In the absence of evidence to the contrary from either party, I infer that the burden would ordinarily be on the defendant to automatically forward the relevant drawings to the plaintiff without the plaintiff having to request for them from the defendant each time. The defendant is fully aware of the scheduled dates by which the various drawings should be made available to the plaintiff. Given that the plaintiff is able to adduce evidence of at least one instance where there was a delay in the issuance of drawings, I agree that liability is prima facie made out and I therefore send this claim down for assessment of the losses (if any) due to the idle time whilst waiting for the drawings to be issued. |
3. | Delay in delivery of materials | The plaintiff is confining its claims to those as stated in Exhibit D11, where the defendant has admitted to a delay but alleges that it is not a critical delay. During trial, there were assertions made by Morris that there were workers and machinery sitting around idle.
This was not challenged. | In order to establish its claim for losses arising out of idle time, the plaintiff has to adduce evidence that it actually had idle workers and machinery. Given that it has failed to do so, the claim must be dismissed. | I send this claim down for assessment since the plaintiff is confining its claims only to those items where liability for the delay in the delivery of the materials has been accepted by the defendant. Further, Morris made certain unchallenged assertions during trial that he had observed idle workers and machinery as a result of these delays. Accordingly, there is sufficient evidence to establish a prima facie case of liability. I note however that it is incumbent on the plaintiff to adduce evidence at the assessment stage to prove exactly how much losses it had incurred due to idle time whilst waiting for the materials to be delivered by the defendant. |
103 Project | ||||
4. | Losses incurred by the plaintiff as a result of the defendant’s delay in its issuance of drawings and materials. | The plaintiff relies mainly on the expert report of Mr Koh Beng Soon (“Koh”) who found that the defendant was indeed late in the issuance of drawings
and materials.
| The tables that the plaintiff relies on to allege delay were meaningless – there is no analysis of whether the date of issuance of any of the first version drawings and/or materials has resulted in any delay at all, or the extent of such a delay.
| The findings of the defendant’s own expert witness, Koh, are naturally not challenged by the defendant. Therefore, there is sufficient evidence to establish a prima facie case that the defendant is liable for delays in the issuance of drawings and materials. Accordingly, I send this claim down for assessment of the losses (if any) due to the idle time whilst waiting for the drawings to be issued or the materials to be delivered by the defendant. |
S/N | Description of claim | Plaintiff’s case | Defendant’s case | Decision |
030 Project | ||||
1. | Wasted costs incurred by the plaintiff due to the defendant taking away the erection part of the contract. | The plaintiff alleges that the fabrication of the PG beam was surreptitiously included in the main purchase order (“PO”).
The plaintiff had initially clarified with the defendant whether the fabrication of the PG beam was indeed necessary and the defendant stated that it was not. Thereafter, the defendant changed its position and said that the plaintiff would have to fabricate the PG beam. However, because of this sudden need to fabricate the PG beam, the plaintiff was not able to complete by the original stipulated date. On account of the plaintiff’s inability to finish the works in time, the defendant took away the erection part of the contract and awarded it to someone else. | Documentary evidence shows that the fabrication of the PG beams had been included in the PO since as early as 14 July 2015. The plaintiff had signed the main PO for the 030 Project which expressly included the PG beam.
It was agreed between parties during a meeting on 3 November 2015 (the “3 November Meeting”)that the erection part of the contract would be taken away.
| The parties had clearly agreed that the erection works would be removed and that the plaintiff would be paid 60% of the original contract sum for the fabrication works. The issue concerning the PG beam had already been raised before the 3 November Meeting. Given that there is no evidence to show otherwise, the logical inference is that the PG beam issue or dispute would be covered by the settlement agreement reached on the 3 November Meeting. Further, I do not accept the plaintiff’s argument that it had reserved its right during the 3 November Meeting to subsequently claim for wasted costs arising out of the removal of the erection part of the contract. Therefore, I dismiss the plaintiff’s claim for wasted costs. |
2. | Plaintiff’s claim for 60% of contract price amounting to $432,573.48, for the fabrication works allegedly completed. | There is no dispute that the parties had agreed for 60% of the original contract sum to be paid for the fabrication works. The plaintiff has completed the fabrication works but has not yet been paid. | There is documentary evidence to prove that certain fabrication works had not yet been completed by the plaintiff. For example, an assembly drawing specified for the beams to be delivered as one item but it was delivered as two separate items.
Additionally, the plaintiff has admitted that it did not complete all the fabrication works
and hence the plaintiff should not be entitled to the entire sum claimed. | Taking the plaintiff’s case at its highest, assuming that it has completed all the fabrication works, I enter judgment for $432,573.48. However, this judgment is to be stayed pending the outcome of the assessment stage where the costs incurred by the defendant to complete any uncompleted portion of the fabrication works will have to be set off against this judgment sum. I note that the defendant’s witness had adduced cogent and convincing evidence that some of the fabrication works was not fully completed. Therefore, this judgment sum is subject to any set offs for uncompleted works or defects counterclaimed by the defendant, to be determined at the assessment stage. |
103 Project | ||||
3. | $109,206 for completed works that have been invoiced but yet to be paid. | The plaintiff has completed the required works in the 103 Project and has invoiced the defendant for $109,206 but the defendant has yet to make payment. | The defendant is not disputing that this sum is owed but that it can be set off from the final amount due to the defendant. | I enter judgment for the sum of $109,206 to be paid by the defendant to the plaintiff. Judgment is to be stayed pending the outcome of the assessment stage. The defendant’s counterclaims for this project as assessed at the assessment stage are to be consolidated and set off from this amount. |
S/N | Variation claim | Plaintiff’s case | Defendant’s case | Decision |
Jangkrik Project | ||||
1. | LGT-MPW-SP-005 | This claim was withdrawn by the plaintiff during the further hearing on 24 August 2018. | ||
2. | LGT-MPW-SP-007 | Payment for this variation work should be based on labour costs as opposed to additional steel weight. This is because the additional steel parts installed are relatively lightweight. However, the costs involved in having to re-mobilise the labour, to re-analyse the revised drawing and then to carry out the reworks are far greater than the payment based on the additional steel weight. | The contract is a measurement contract. Therefore the final price inclusive of all variations should be calculated based on the final weight of steel and not based on the additional labour or time expended for the variation work. | I find merit in the plaintiff’s argument that this variation work involves a lot of work but the final increase in weight is relatively small. The plaintiff has produced evidence showing that the incremental steel weight arising from this variation is small. I note that it leads to an unfair situation where the variation ordered to be done pursuant to a revised drawing issued by the defendant requires a lot of labour but contributes to a relatively low increase in weight as is the case here. I accept that this is a measurement contract based on the steel weight as agreed between the parties. But the price per ton of steel to be fabricated has been worked out and agreed by the parties based on a certain complexity of the fabrication work as understood by the parties. Where revised drawings subsequently issued by the defendant give rise to variation works that increase the complexity of the steel work without much increase to the steel weight, then the plaintiff is unduly taken advantage of, unless the defendant can point to a specific clause in their measurement contract that clearly stipulates that any subsequent variation work is to be similarly priced based on the additional steel weight. This the defendant is not able to. Furthermore, if the variation involves work to cut out materials thereby leading to a reduction in the total steel weight, it could lead to the absurd situation where the plaintiff doing the extra work effectively has to pay the defendant for ordering such a variation work if I were to adopt the defendant’s proposed method of pricing for the variation work based on the total steel weight. In the absence of a specific clause stating clearly that variations are to be priced based on the changes to the steel weight occasioned by the variation work, I conclude that the variations are to be priced on a quantum meruit basis and not on the basis of any addition/reduction of the total steel weight occasioned by the variation. Accordingly, I send this claim down for assessment to determine on a quantum meruit basis the amount of labour cost expended for this variation. Before allowing the plaintiff’s claim for labour cost for the variation work, the plaintiff is to refund to the defendant whatever it has been paid in relation to any increase in the weight of steel occasioned by the variation so as to avoid any double payment to the plaintiff. |
3. | LGT-MPW-SP-009: Purported addition of stiffeners allegedly resulting from the defendant’s revised drawings | For the same reasons given in s/n 2 above, I send this claim down for assessment to determine on a quantum meruit basis the amount of labour cost expended for this variation. Before allowing the plaintiff’s claim for labour cost for the variation work, the plaintiff is to refund to the defendant whatever it has been paid in relation to any increase in the weight of steel occasioned by the variation so as to avoid any double payment to the plaintiff. | ||
4. | LGT-MPW-SP-013 | Same as for s/n 3 above. | ||
5. | LGT-MPW-SP-014 | Same as for s/n 3 above. | ||
6. | LGT-MPW-SP-015 | Same as for s/n 3 above. | ||
7. | LGT-MPW-SP-021: Alleged reworks for levels 2, 3 and 4 of the E-House module. | Same as for s/n 3 above. | ||
7. | LGT-MPW-SP-029 | This is a duplicate claim and should not be allowed.
| I send this claim down for assessment. The burden is on the defendant to adduce evidence to show that this is indeed a duplicate claim. | |
8. | LGT-MPW-SP-035: re-orientation of pillars | This claim was withdrawn by the plaintiff during the further hearing on 24 August 2018. | ||
9. | LGT-MPW-SP-038: Claim for cutting plan | The contract specifically states that “cutting list/plan” is to be prepared by the defendant for the beams. Without a cutting plan, the plaintiff could not carry out the cutting of the beams from the raw materials in a manner which would minimise wastage.
| The defendant did not request the plaintiff to prepare a cutting plan, nor was one required to carry out the works for the Jangkrik Project. The Jangkrik contract merely states that the defendant would “check” the cutting plan if the plaintiff so decides to prepare one.
| The scope matrix states that it is the defendant’s responsibility to prepare a “cutting list/plan”. There are two possible interpretations that can arise from this: first, that the defendant is to prepare a cutting list “or” a cutting plan; second, that the defendant is to prepare a cutting list “and” a cutting plan. I note that the other projects which had beams and plates required both cutting lists and cutting plans. Therefore, given that the Jangkrik Project also had both beams and plates, I infer that it would also require both cutting lists and cutting plans. Therefore, I find that the cutting plans are works that the defendant would have required. I therefore send this variation claim down for assessment to determine what is the reasonable cost for such works. |
030 Project | ||||
11. | LGT-STR-VO-0014 | All the variation claims relating to the 030 Project were withdrawn by the plaintiff during the further hearing on 24 August 2018 on the basis that it did not have evidence before the court to support these claims. | ||
12. | LGT-STR-VO-0015 | |||
13. | LGT-STR-VO-0016 | |||
14. | LGT-STR-VO-0017 | |||
15. | LGT-STR-VO-0018 | |||
16. | LGT-STR-VO-0019 | |||
17. | LGT-STR-VO-0020 | |||
18. | LGT-STR-VO-0021 | |||
19. | LGT-STR-VO-0022 | |||
20. | LGT-STR-VO-0023 | |||
21. | LGT-STR-VO-0024 | |||
22. | LGT-STR-VO-0025 | |||
23. | LGT-STR-VO-0026 | |||
24. | LGT-STR-VO-0027 | |||
25. | LGT-STR-VO-0028 | |||
26. | LGT-STR-VO-0029 | |||
27. | LGT-STR-VO-0030 | |||
28. | LGT-STR-VO-0031 | |||
29. | LGT-STR-VO-0032 | |||
30. | LGT-STR-VO-0033 | |||
31. | LGT-STR-VO-0034 | |||
32. | LGT-STR-VO-0035 | |||
33. | LGT-STR-VO-0036 | |||
34. | LGT-STR-VO-0037 | |||
35. | LGT-STR-VO-0038 | |||
36. | LGT-STR-VO-0039 | |||
37. | LGT-STR-VO-0040 | |||
38. | LGT-STR-VO-0041 | |||
39. | LGT-STR-VO-0042 | |||
40. | LGT-STR-VO-0043 | |||
41. | LGT-STR-VO-0044 | |||
42. | LGT-STR-VO-0045 | |||
103 Project | ||||
43. | LGTWP-STR-VO-008: Costs incurred for having to transport excess material back to the defendant. | The defendant by mistake delivered about double the required quantities of materials to the plaintiff.
Therefore, the plaintiff had to incur additional costs to transport these excess materials back to the defendant. | The defendant rejected the claims because “[i]n accordance with [the Plaintiff’s] responsibility scope matrix item B.25 ‘Any offcut or unused materials shall be returned through MRN (material return note) to [the Defendant’s] Store…’”
This is therefore the plaintiff’s responsibility. | From the outset, I informed parties that I will only allow these claims if the amount of excess material delivered by the defendant is unreasonable when compared to the total weight of the project. The total weight of the excess material for claims LGTWP-STR-VO-008 and LGTWP-STR-VO-009 is128 tonnes. The total weight of the project is 637 tonnes. This means that the excess material amounted to only about 20% of the total weight of the project. I note that this does not include the weight of the excess material from the LGTWP-STR-VO-010 claim because such evidence is not before the court. Nevertheless, I do not think that the weight of the excess material is so unreasonable as to require the defendant to compensate the plaintiff for the transport costs. Therefore I dismiss these claims. |
44. | LGTWP-STR-VO-009 | |||
45. | LGTWP-STR-VO-010 | |||
46. | LGTWP-STR-VO-012 | This claim was withdrawn by the plaintiff during the further hearing on 2 August 2018. |
S/N | Variation Claim | Decision |
Jangkrik Project | ||
1. | LGT-MPW-SP-001 | Variation claim is to be sent for assessment on a quantum meruit basis. |
2. | LGT-MPW-SP-002 | As in s/no 1 above. |
3. | LGT-MPW-SP-003 | As in s/no 1 above. |
4. | LGT-MPW-SP-004 | As in s/no 1 above. |
5. | LGT-MPW-SP-008 | As in s/no 1 above. |
6. | LGT-MPW-SP-010 | As in s/no 1 above. |
7. | LGT-MPW-SP-012 | As in s/no 1 above. |
8. | LGT-MPW-SP-019 | As in s/no 1 above. |
9. | LGT-MPW-SP-011 | As in s/no 1 above. |
10. | LGT-MPW-SP-017 | As in s/no 1 above. |
11. | LGT-MPW-SP-020 | As in s/no 1 above. |
12. | LGT-MPW-SP-021 | The defendant has accepted liability only for the variation works done to level 1 and disputed its liability with respect to those at other levels.
quantum meruit basis only for the variation works done to level 1. Therefore, this variation claim is to be sent for assessment on a |
13. | LGT-MPW-SP-028 | As in s/no 1 above. |
14. | LGT-MPW-SP-025 | As in s/no 1 above. |
15. | LGT-MPW-SP-030 | As in s/no 1 above. |
16. | LGT-MPW-SP-031 | As in s/no 1 above. |
17. | LGT-MPW-SP-032 | As in s/no 1 above. |
18. | LGT-MPW-SP-033 | As in s/no 1 above. |
19. | LGT-MPW-SP-034 | As in s/no 1 above. |
20. | LGT-MPW-SP-036 | As in s/no 1 above. |
21. | LGT-MPW-SP-037 | As in s/no 1 above. |
22. | LGT-MPW-SP-038 | The defendant has accepted liability only for the weld maps but does not accept liability for the cutting plans.
quantum meruit basis only for the weld maps. Accordingly, this variation claim is to be sent for assessment on a |
103 Project | ||
23. | LGTWP-STR-VO-001 | As in s/no 1 above. |
24. | LGTWP-STR-VO-002 | As in s/no 1 above. |
25. | LGTWP-STR-VO-003 | As in s/no 1 above. |
26. | LGTWP-STR-VO-004 | As in s/no 1 above. |
27. | LGTWP-STR-VO-005 | As in s/no 1 above. |
28. | LGTWP-STR-VO-006 | As in s/no 1 above. |
29. | LGTWP-STR-VO-007 | As in s/no 1 above. |
30. | LGTWP-STR-VO-011 | As in s/no 1 above. |
31. | LGTWP-STR-VO-013 | As in s/no 1 above. |
S/N | Description of claim | Plaintiff’s case | Defendant’s case | Decision |
Jangkrik Project | ||||
1. | Liquidated damages for delay to the Jangkrik Project. | The plaintiff submits that it should not be liable for liquidated damages given that the delay is caused by the defendant itself. | It is not disputed that the actual completion of the Jangkrik Project is delayed. Given that there is no merit in the delay claims made by the plaintiff, the delay should be wholly attributable to the plaintiff. | I adopt fully Koh’s expert report with regard to Koh’s assessment of the delays based on his critical path analysis and his assessment of the number of days of delay qualifying for the imposition of liquidated damages. I enter judgment for $37,178.43 to be paid by the plaintiff to the defendant. Judgment is to be stayed pending the outcome of the assessment stage for other claims and counterclaims (if any). |
2. | Back charges for providing the plaintiff with two welders from 8 to 30 April 2015. | The defendant did not adduce any supporting evidence to substantiate the amount of this counterclaim
| Counsel for the plaintiff has admitted that the defendant had provided two welders to assist the plaintiff to carry out the works.
| Given that counsel for the plaintiff has admitted as a matter of fact that the defendant did indeed provide two welders to the plaintiff for carrying out the works, I see no good reason to deprive the defendant of this claim. I also note that it was always open to the plaintiff at that time to reject the two welders if it did not need them to assist. However, given that it had not rejected the welders, the plaintiff is under an obligation to pay for the costs of these two welders supplied by the defendant to assist in the plaintiff’s welding works. As for the additional or repeat tests that the defendant had to conduct because of the defective welds, I am satisfied by the documentary evidence that such tests were done and paid for by the defendant. Accordingly, I enter judgment for a total of $29,992.00 for both these counterclaims, to be paid by the plaintiff to the defendant. Judgment is to be stayed pending the outcome of the assessment stage for other claims and counterclaims (if any). |
3. | Back charges for additional inspection costs (non-destructive testing) necessitated by the purported defects. | This counterclaim is not pleaded. Further, there is no evidence adduced to support it.
| There is evidence in the form of a purchase order for costs incurred in hiring PT Jasscan Indonesia to carry out non-destructive testing.
| |
030 Project | ||||
4 | Overpayment to the plaintiff due to the plaintiff’s failure to complete the fabrication works which have already been paid for. | I make no order with respect to this claim. I reiterate that the defendant is to pay the entire contract sum to the plaintiff, subject to any sums that are to be subtracted for uncompleted or defective works which are to be assessed at the assessment stage. | ||
5. | Rectification costs for defective works that the plaintiff had failed or refused to rectify. | I consider the defective work here to include not only repair work to remedy defects in the plaintiff’s work but also work that the plaintiff has left uncompleted, where the defendant had to engage manpower resources to finish the uncompleted work. I send this claim down for assessment. The quantum of damages assessed shall be set off against the judgment sums obtained by the plaintiff for the 030 Project. | ||
6. | Damages arising from the delay to the 030 Project which is attributable to the plaintiff. | The delay is attributable to the defendant. The plaintiff completed the fabrication works on 30 November instead of 15 November 2015 because it was waiting for the necessary materials from the defendant.
| There is no dispute that the 030 Project was delayed. Prakash testified that the delay was caused by the plaintiff’s slow progress.
| I find that there is prima facie evidence of a delay by the plaintiff in the completion of the 030 Project even after the delivery schedule was revised pursuant to the settlement agreement entered into during the 3 November Meeting. Therefore, I send this claim down for assessment. If the plaintiff wishes to show that this delay (or a part thereof) is caused by the defendant, then the burden is on the plaintiff to do so. The damages (if any) eventually awarded to the defendant are to be set off against the judgment sums obtained by the plaintiff for the 030 Project. |
103 Project | ||||
7. | Refund of $226,200 paid by defendant for acceleration of works, which was not eventually done. | The defendant has not shown any evidence that the plaintiff did not accelerate the works. The defendant would not have paid if indeed the plaintiff had not accelerated the works. Koh’s expert report stated that the plaintiff had provided more manpower than required under the purchase order issued by the defendant for the plaintiff to provide more manpower to accelerate the works.
| The plaintiff had failed to meet all but one of the new milestone dates as agreed pursuant to the purchase order for the acceleration of the works.
| The purchase order for the acceleration of the works was issued on 4 November 2015, one day after the 3 November Meeting where parties had agreed to settle all commercial issues. Therefore, I find that the sum paid for the acceleration is part of the settlement agreement. Accordingly, I dismiss this claim for a refund of the amount paid for acceleration works. If there is a failure on the plaintiff’s part to meet any subsequent milestones after the acceleration payment was made, it is open to the defendant to claim liquidated damages for these subsequent delays. |
8. | Liquidated damages arising from delays in the project caused by the plaintiff. | The plaintiff submits that it should not be made liable for liquidated damages given that the delay is caused by the defendant itself. | There is no dispute that the actual completion for the 103 Project was delayed. Prakash testified that the plaintiff’s slow progress caused the delays. The defendant’s expert witness Koh’s assessment of the period of delay was unchallenged by the plaintiff.
| I adopt fully Koh’s expert report with regard to Koh’s assessment of the delays based on his critical path analysis and his assessment of the number of days of delay qualifying for the imposition of liquidated damages. I enter judgment for $19,671.69 to be paid by the plaintiff to the defendant. Judgment is to be stayed pending the outcome of the assessment stage for other claims and counterclaims (if any) for the 103 Project. |
9. | Rectification costs for defective works that the plaintiff had failed to rectify. | There was no documentary evidence from the defendant showing that the plaintiff was notified of these defects. The third party contractors engaged to rectify these defects were not called as witnesses.
| The punch list lists defects in the plaintiff’s works that required grinding in the area “Canopy Roof and Top Crimped Wall PAB-103 at EL 114.950 and below”. Invoices from one of the third party contractors show that the defendant had to carry out “grinding underneath secondary below roof grid 3-4-5 row A-B”.
| I accept the evidence provided by the punch list and the third party invoices showing that the defendant had to rectify the defective works of the plaintiff. I send this down for assessment. The amount that is allowed is similarly to be set off against the judgment sums awarded to the plaintiff for the 103 Project. |
Jangkrik Project | |
Claims | |
Variation works | To be assessed |
Losses from idle time due to delays caused by the defendant | To be assessed |
Counterclaims | |
Liquidated damages for delay | $37,178.43 |
Back charges for costs of additional welders and inspections | $29,992.00 |
030 Project | |
Claims | |
Work done for the 030 Project amounting to 60% of the original contract price | $432,573.48 |
Variation works | Entirely withdrawn by the plaintiff |
Wasted costs due to removal of erection works | Claim dismissed |
Counterclaims | |
Overpayment | No order |
Back charges for rectification costs | To be assessed |
Damages for delay in completion | To be assessed |
103 Project | |
Claims | |
Work done for the 103 Project | $109,206 |
Variation works | To be assessed |
Losses from idle time due to delays caused by the defendant | To be assessed |
Counterclaims | |
Liquidated damages for delay | $19,671.69 |
Refund of monies paid to accelerate works | Claim dismissed |
Back charges for rectification costs | To be assessed |
This judgment text has undergone conversion so that it is mobile and web-friendly. This may have created formatting or alignment issues. Please refer to the PDF copy for a print-friendly version.
Version No 2: 27 Oct 2020 (22:40 hrs)